Description
Task/Activity Dependencies:
It is expected that you will find the correct task dependencies based on the
material discussed during class and considering the following constraints:
1. There is no technical task prior to requirement phase; project
planning is not a technical task it is a managerial task.
2. Analysis Activity can start as soon as requirement document is
complete
3. Design activity can start as soon as Analysis document is complete
4. Data Model task can start when Detailed Design task finishes
5. Coding can start as soon as design is complete
6. Writing Test Plan can start as soon as requirements are complete
7. Executing Test Plan can start as soon as coding is complete
8. Documentation can start as soon as requirements are complete
9. Any other constraints that you might add, shall be documented
clearly when you submit your homework.
10. Risk mitigation and contingency planning can start after project
plan is complete, and can finish any time before analysis starts.
Task Amount of Work Productivity Rate
Project Plan
Write Plan 129 pages 2 pages/Hour
Review Plan
Preparation for review 5 pages/Hour
Review Meeting 6 pages/Hour
Rework 61 defects 10 defects/Hour
Risk Mitigation and Contingency Plan
Write Plan 21 pages 2 pages/Hour
Review Plan
Preparation for review 4 pages/Hour
Review Meeting 8 pages/Hour
Rework 23 defects 4 defects/Hour
Requirement
Write requirements 145 Req 3 Req/Hour
Write Use Case Model 109 Use Cases 1 use case/4 Hours
Review Requirements/ Use Case Model
Preparation for review 25 Req/Hour
5 Use Cases/Hour
Review Meeting 30 Req/Hour
10 Use Cases/Hour
Rework 137 defects 5 defects/Hour
Analysis
Write Analysis Document 119 pages 5 pages/Hour
Review Analysis Document
Preparation for Analysis Document 5 pages/Hour
Review Meeting 10 pages/Hour
Rework 84 defects 7 defects/Hour
Design
Write DD 147 pages 3 pages/Hour
Review DD
Preparation for DD 5 pages/Hour
Review Meeting 8 pages/Hour
Rework 132 defects 5 defects/Hour
Write Data Model (DM) 37 pages 1 page/5 Hours
Review DM
Preparation for DM 3 pages/Hour
Review Meeting 6 pages/Hour
Rework 59 defects 5 defects/Hour
Coding and unit test
Write Code 4177 SLOC 5 SLOC/Hour
Unit Testing
Prepare/Execute Test Cases 243 test cases 8 Test Cases/Day
Fix Found Defects 142 Defects 8 Defects/Day
Test Fixed Defects 142 Defects 4 Defects/Day
Code Inspection
Preparation for Code Inspection 150 SLOC/Hour
Code Inspection Meeting 200 SLOC/Hour
Rework 167 defects 5 defects/Hour
Testing
Write test plan (TP) 163 pages 5 pages/Day
Review TP
Preparation for TP 5 pages/Hour
Review TP Meeting 10 pages/Hour
Rework 215 defects 5 defects/Hour
Execute TP (test cases) 217 test cases 8 test cases/day
Fix Found Defects 136 defects 5 defects/day
Test Fixed Defects 136 defects 10 defects/day
Documentation
User Documentation 273 pages 2 pages/Hour
Review UD
Preparation for UD Review 8 pages/Hour
Review UD Meeting 10 pages/Hour
Rework 319 defects 23 defects/Hour